Power Grid

Ilijan–Tayabas 500 kV line — unexplained conductor severing

13 May 2026 · Approximately 06:30 local time

Batangas City, Batangas, Philippines (approximate location)

What happened

The Ilijan–Tayabas 500 kV line tripped after a conductor between Towers 129 and 130 in Barangay Haligue Silangan was found severed. It followed the Dasmariñas–Ilijan line trip earlier that morning. NGCP said the physical condition warranted a police investigation and that sabotage could not be ruled out, but the root cause remained under investigation. The two line trips contributed to Luzon and Visayas grid alerts and rotating outages, though NGCP stressed that numerous generating plants were also unavailable. The reviewed evidence does not support assigning the roughly 1,700 MW figure to this severed line; the marker is approximate.

When cited sources give different casualty, damage or spill figures for this event, they’re reported side by side above rather than merged into one number. See how confidence levels work.

Evidence
Under investigation
Confidence
Unverified
Infrastructure
Power Grid
Latitude
13.7600°
Longitude
121.0600°

Attribution

Responsibility disputed Unknown; possible deliberate intervention under investigation

The grid operator asked police to investigate possible sabotage, but no perpetrator or deliberate cause had been established in the reviewed reporting.

Sources

  1. NGCP seeks police probe into possible sabotage of Ilijan–Tayabas 500kV lineBusinessMirror; Manila Bulletin; Philippine News Agency · Incident reporting