Power Station
Barapukuria Unit 1 — repeat boiler-tube rupture
2 May 2026 · Saturday night
Dudhipur, Parbatipur, Dinajpur, Bangladesh
Map
25.5538, 88.9486
What happened
Another boiler tube ruptured in Barapukuria's 125 MW Unit 1 on Saturday night, less than 24 hours after the unit resumed following repairs to its 25 April tube failure. The repaired unit had returned at about 22:00 on 1 May and was supplying 55–60 MW to the national grid. With Unit 2 out of service for years and Unit 3 under overhaul, the new rupture again stopped all electricity generation at the 525 MW plant. Officials did not disclose the shutdown until 4 May and estimated roughly five days to cool the overheated boiler water and replace the damaged tube. No casualties were reported. Reporting described frequent mechanical faults and noted that the plant has never sustained operation at its full installed capacity.
When cited sources give different casualty, damage or spill figures for this event, they’re reported side by side above rather than merged into one number. See how confidence levels work.
- Evidence
- Documented
- Confidence
- High
- Infrastructure
- Power Station
- Current temperature
- Loading…
- Latitude
- 25.5538°
- Longitude
- 88.9486°
Attribution
Responsibility has not been established in the cited reporting.
Sources
- Barapukuria power plant shuts down again after boiler tube explosionThe Business Standard · Incident reporting
- Barapukuria power plant shuts down again after boiler tube explosionDhaka Tribune · Corroborates the repeat rupture, complete halt and repair estimate
- Barapukuria power stationGlobal Energy Monitor · Facility ownership, repeated-fault history and exact-coordinate reference